The Courage Behind Boeing’s Dreamliner Project

I’m sure many of you heard about the Boeing 787 Dreamliner that made its first commercial journey on 26 October. It is the most technologically advanced commercial airplane and enables air travel that is cheaper, faster and more comfortable.

Perhaps you also heard about the process, communications and quality issues that delayed the project by three years and cost the company close to US$10 billion in overrun charges, according to the business news outlet Bloomberg.

As a project manager, what jumps out to me is the fortitude of Boeing’s management to ensure a quality product — despite extraordinary pressure.

I have no doubt that if it had wanted to, Boeing could have completed this project earlier. But rather than take shortcuts and risk potential issues, it held out for a product that met its standards.

Much attention has focused on Boeing’s attempts to save money and to secure global accounts by outsourcing a large portion of its component manufacturing and design. The idea was that assembly and time to market would be accelerated by allowing various parts of the plane to be flown to Boeing’s facility in Seattle, Washington, USA. There, they could be pieced together in order. According to news reports, the move initially netted Boeing nearly 1,000 orders and helped keep its prime competitor, Airbus, at bay.

But it marked a big change in Boeing’s existing process to keep almost all of its engineering design in-house. The company typically delivers very specific “build-to-order” instructions to its manufacturing partners, outlining specifications and direction, and then collaboratively designing the parts.

There were many challenges associated with a project as complex and pioneering as the Dreamliner project. One example is the process for oversight and quality control of multiple, globally based contractors. Issues arose, such as contractors subcontracting to suppliers who couldn’t meet deadlines or quotas. In other cases, contractors shipped parts that wouldn’t fit together correctly.

Think about it: In my opinion, Boeing realized that it was more important to get the project done right versus done fast. And while the company has faced criticism, suffered some embarrassment and, yes, spent more than it anticipated, these are all short-term issues.

In the long run, I believe the project will bolster Boeing’s reputation for quality. It will also have finely tuned a project management process that should bring the company much higher returns in the future.

Article source: http://blogs.pmi.org/blog/voices_on_project_management/2011/11/the-courage-behind-boeings-dre.html